Resort Update
The first half of 2019 has been very productive with resort updates. In the spring, we completed resurfacing the outdoor pool and hot tub areas for your summer enjoyment. New flooring and furniture have been installed in buildings 2,3,4,5,6 and 7.
For the remainder of 2019 and into 2020, we will continue with replacing the flooring and furniture in buildings 8 through 12. This includes replacing both soft and hardwood flooring, along with providing new sofas and love seats. Below we have provided the schedule for phase two. If you notice that these dates affect your stay, we are here to work with you to accommodate your vacation time in a different building.
BUILDING EIGHT
Flooring & Living Room Soft Seating: October 27th – November 10th, 2019
BUILDING NINE
Flooring & Living Room Soft Seating: November 10th – 24th, 2019
BUILDING TEN
Flooring & Living Room Soft Seating: December 1st – 15th, 2019
BUILDING ELEVEN
Flooring & Living Room Soft Seating: January 5th – 19th, 2020
BUILDING TWELVE
Flooring & Living Room Soft Seating January 19th – February 2nd, 2020
Other Stories
Spring 2024 Unit Updates
We’ve been actively enhancing your timeshare units this spring, using your maintenance fees to elevate the quality of your ownership experience. These updates are designed to enrich your next visit to Meadow Lake. We encourage […]
GM Letter December 2023
Dear Meadow Lake Owners: Season’s greetings from beautiful northwest Montana. It is my pleasure to write to you as winter comes calling. We’ve had a great year, and we are looking forward to 2024. Our […]
Document Change Presentation with Q&A
Document Change Presentation 4/1/2022 Q&A From Presentation QUESTION 1 From Joanne to Me (Direct Message) 12:01 PM Will you be opening up the chat so the entire group can see […]