Resort Update 01-23-20

MLDC is committed to retaining the value of your ownership at Meadow Lake Resort. 2019 was very busy with ongoing resort renovations.  In the spring, we completed resurfacing the outdoor pool and hot tub areas for your summer enjoyment. Also, new flooring and furniture have been installed in buildings 2,3,4,5,6,7,8,9 and 10.

For the remainder of 2020, we will continue with replacing the flooring and furniture in buildings 11 and 12. This includes replacing both soft and hardwood flooring, along with new sofas and love seats.  If you notice that these dates affect your stay, we are here to work with you to accommodate your vacation time in a different building.

BUILDING ELEVEN

Flooring & Living Room Soft Seating: January 5th – 19th, 2020

BUILDING TWELVE

Flooring & Living Room Soft Seating January 19th – February 2nd, 2020

As part of the flooring project, the coffee and end tables will be refinished in buildings 2 through 12 throughout 2020.

In addition, we will complete a variety of work within units in Buildings 2 through 7.  Specifically, we will replace the valances in buildings 2 and 3, where the existing valances are either outdated or have outlasted their life. These valances will be replaced with a wood material to coincide with the updated décor of the unit. Also, the full wall dining room mirror will be reduced in size, centered and framed to match the new valances.  Both of these projects were started several years ago and we are excited to have them completed this year.

BUILDING TWO

Living and Dining Area Window Valances: Spring 2020

BUILDING THREE

Living and Dining Area Window Valances: Spring 2020

BUILDING FIVE

Dining Room Mirror Framed: Spring/Early Summer 2020

BUILDING SIX

Dining Room Mirror Framed: Spring/Early Summer 2020

BUILDING SEVEN

Dining Room Mirror Framed: Spring/Early Summer 2020

Lastly, we have begun the process of selecting flooring and living room soft seating for Nenastako Village in anticipation of starting work in the Fall/Winter of 2020.  More details and a schedule of this work will be posted to our website soon, so please be sure to check regularly.  We are very excited for this project as it will complete the installation of new flooring throughout the entire resort excluding only the newest of the buildings, Glacier Village.

Other Stories

GM Letter December 2023

March 25th, 2024|0 Comments

Dear Meadow Lake Owners: Season’s greetings from beautiful northwest Montana. It is my pleasure to write to you as winter comes calling. We’ve had a great year, and we are looking forward to 2024. Our […]

Governing Document Change FAQ

February 8th, 2022|0 Comments

Since Meadow Lake’s creation in the 1980s, much has changed in the world as well as the world of vacation ownership. As a result, some of the features of ownership that were a strength at […]